UK carrier progamme costs increase as PoW build nears completion
Although the build and outfitting of HMS Prince of Wales, the second of the UK’s new class of aircraft carrier, continues broadly on schedule, budgetary pressures still shadow the long-running programme.
According to the UK Ministry of Defence (MoD) 2018 Equipment Plan released on 5 November, the Queen Elizabeth-class carrier programme saw an increase of £149 million ($195 million) to its budget, based on 2017/2018 aggregate forecasts.
Initially budgeted to cost around £3.5 billion, the programme is now expected to cost the UK taxpayer in excess of £6 billion by its close.
Further, the report stated that UK
Already have an account? Log in
Want to keep reading this article?
Read this Article
Get access to this article with a Free Basic Account
- Original curated content, daily across air, land and naval domains
- 2 free stories per week
- Daily news round-up email service
- Access to all Decisive Edge email newsletters
Unlimited Access
Access to all our premium news as a Premium News 365 Member. Corporate subscriptions available.
- Original curated content, daily across air, land and naval domains
- 14-day free trial (cancel at any time)
- Unlimited access to all published premium news
More from Naval Warfare
-
UK and US marines train to guard nuclear deterrent submarines
The Autumn round of Tartan Eagle training just concluded in Scotland.
-
Saab and Singapore DSTA expand their understanding on undersea defence
The organisations have broadened the remit of an existing MoU to help boost underwater defence innovation.
-
Norway invites four nations to talk partnerships over new frigates
The US, the UK, France and Germany each have existing frigate programmes.