Malaysia considers whether to stick or twist with LCS
The Malaysian Ministry of Defence (MINDEF) is mulling how to proceed with its troubled Maharaja Lela -class Littoral Combat Ship (LCS) programme.
None of the six LCS vessels on order from Boustead Naval Shipyard have been successfully completed, Defence Minister Datuk Seri Ismail Sabri Yaacob told parliament on 3 August.
LCS 1 is almost 60% completed, ahead of LCS 2 (48%), LCS 3 (43.75%), LCS 4 (36.49%) and LCS 5 (20%). Construction of LCS 6 is yet to begin.
This means that the overall programme is some 31 months behind schedule, Ismail Sabri said, and costs are spiralling beyond the original MYR9.13 billion ($2.16 billion) contract ceiling.
The LCS project faces a Cabinet-level review, with three options in play.
‘The first option is for the project to be continued by appointing Naval Group France as a rescue contractor… using the remaining contract ceiling to complete at least two LCS units,’ Ismail Sabri said.
Alternatively, Boustead Naval Shipyard would be required to complete ‘at least two LCS units’ within the remaining contract ceiling, he added.
The third option is to terminate the contract entirely, with the government stepping in the save the LCS programme.
Ismail Sabri said that saying that MINDEF does not intend to inject additional funds for Bousted Naval Shipyard to complete the LCS programme, despite a request from the shipbuilder.
However, the government could pay for the design rights and complete construction itself.
As part of our promise to deliver comprehensive coverage to our Defence Insight and Premium News subscribers, our curated defence news content provides the latest industry updates, contract awards and programme milestones.
Related Programmes in Defence Insight
Maharaja Lela Class [Malaysia]
Related Equipment in Defence Insight
More from Naval Warfare
-
Second rMCM vessel begins sea trials, advances autonomous minesweeping
The rMCM programme will ultimately comprise of 12 vessels, six each working for the Belgian and the Royal Netherlands Navy.
-
Long-delayed polar icebreaker programme gets cash and impetus boost
The US Government has awarded a significant contract to move along its Polar Security Cutter programme.
-
Avalon 2025: Kongsberg confirms its first Australian missile factory
The deal, which has been planned since August 2024, is part of an ongoing attempt to bolster Australia’s defences against the potential of Chinese aggression.
-
TKMS joins forces with Norwegian shipbuilder for Fridtjof Nansen frigate replacement bid
Four shipbuilders have been downselected to build the frigate replacement programme, and TKMS hopes the new deal will give it a geographical advantage.
-
As Australian resistance rises, is AUKUS in trouble?
The tripartite submarine project is under political pressure from a grass-roots Australian Labor Party movement, but it could also have practical issues in its way.
-
Newest Arleigh Burke Flight III destroyer launched and ready for fitting
DDG 129, which will become the USS Jeremiah Denton on commissioning, was moved to dry dock to begin its technical fitting and testing.