Malaysia considers whether to stick or twist with LCS
The Malaysian Ministry of Defence (MINDEF) is mulling how to proceed with its troubled Maharaja Lela -class Littoral Combat Ship (LCS) programme.
None of the six LCS vessels on order from Boustead Naval Shipyard have been successfully completed, Defence Minister Datuk Seri Ismail Sabri Yaacob told parliament on 3 August.
LCS 1 is almost 60% completed, ahead of LCS 2 (48%), LCS 3 (43.75%), LCS 4 (36.49%) and LCS 5 (20%). Construction of LCS 6 is yet to begin.
This means that the overall programme is some 31 months behind schedule, Ismail Sabri said, and costs are spiralling beyond the original MYR9.13 billion ($2.16 billion) contract ceiling.
The LCS project faces a Cabinet-level review, with three options in play.
‘The first option is for the project to be continued by appointing Naval Group France as a rescue contractor… using the remaining contract ceiling to complete at least two LCS units,’ Ismail Sabri said.
Alternatively, Boustead Naval Shipyard would be required to complete ‘at least two LCS units’ within the remaining contract ceiling, he added.
The third option is to terminate the contract entirely, with the government stepping in the save the LCS programme.
Ismail Sabri said that saying that MINDEF does not intend to inject additional funds for Bousted Naval Shipyard to complete the LCS programme, despite a request from the shipbuilder.
However, the government could pay for the design rights and complete construction itself.
As part of our promise to deliver comprehensive coverage to our Defence Insight and Premium News subscribers, our curated defence news content provides the latest industry updates, contract awards and programme milestones.
Related Programmes in Defence Insight
Maharaja Lela Class [Malaysia]
Related Equipment in Defence Insight
More from Naval Warfare
-
US Coast Guard enhances Arctic protection with a new Fast Response Cutter
After commissioning, FRC Frederick Mann will operate in Alaska and perform multiple missions.
-
US Coast Guard announces measures to further implement Force Design 2028 strategy
The US Coast Guard (USCG) created new units, including five Programme Executive Offices (PEOs), to facilitate and speed up the procurement of new capabilities.
-
Future of the US Navy’s Arleigh Burke programme remains unclear
The US Navy does not have a precise date for the award of the procurement contract for the third Arleigh Burke-class destroyer despite having the funds to advance with the programme in FY2025.
-
US Navy may look to foreign suppliers to accelerate shipbuilding programmes
The US Navy (USN) is currently reassessing its acquisition efforts and seeking ways to reduce the multiple delays across the shipbuilding initiatives.
-
Italy orders two ships as work begins on others along with deliveries and updates
The Italian Navy is being refreshed with two new ships ordered, while in the past six months steel was cut for a new frigate, an enhanced frigate was delivered and Horizon-class frigates passed a design review.