HMAS Hobart completes builders sea trials
HMAS Hobart, the lead ship of the new Hobart class of Air Warfare Destroyers (AWDs) for the Royal Australian Navy (RAN), has completed its builder sea trials off the South Australian coast.
This marks the latest milestone for the vessel, bringing it closer to final delivery to the RAN. Ship build began in January 2010, followed by hull consolidation in March 2014 and launch in May 2015.
The second destroyer of this class, HMAS Brisbane, will enter the water following its scheduled launch in December 2016. Hull consolidation of the third AWD, Sydney, is scheduled to take place in August 2017.
The AWD Alliance building the ships includes ASC, Raytheon Australia as the combat systems integrator and the Australian Department of Defence's (DoD) Capability Acquisition and Sustainment Group.
The team will now continue consolidating and outfitting the remaining two destroyers. HMAS Hobart will undergo further sea trials in early 2017 to test its advanced combat system, followed by delivery of the destroyer to the DoD in June 2017.
More from Naval Warfare
-
Future of the US Navy’s Arleigh Burke programme remains unclear
The US Navy does not have a precise date for the award of the procurement contract for the third Arleigh Burke-class destroyer despite having the funds to advance with the programme in FY2025.
-
US Navy may look to foreign suppliers to accelerate shipbuilding programmes
The US Navy (USN) is currently reassessing its acquisition efforts and seeking ways to reduce the multiple delays across the shipbuilding initiatives.
-
Australia commissions HMAS Arafura three-and-a-half years behind schedule
The Royal Australian Navy has finally commissioned the first Arafura-class offshore patrol vessel – more than three years behind schedule – highlighting the programme’s delays, design compromises and ongoing industrial restructuring.
-
Italy orders two ships as work begins on others along with deliveries and updates
The Italian Navy is being refreshed with two new ships ordered, while in the past six months steel was cut for a new frigate, an enhanced frigate was delivered and Horizon-class frigates passed a design review.
-
US Navy foresees additional delays in the Columbia-class programme
After estimating that the first Columbia-class submarine would be delivered 16 months late, the US Navy has recently confirmed that an additional month will be required to complete its construction.