DefExpo 2018: Boeing helicopter deliveries on track for India

12th April 2018 - 16:25 GMT | by Gordon Arthur in Chennai

RSS

The first of 22 Boeing AH-64E Apaches for the Indian Air Force (IAF) entered the production line at the company’s Mesa facility in the US on 10 April. Delivery of the first aircraft is on schedule for mid-2019.

Meanwhile, the first of 15 CH-47F Chinooks for India was loaded on the line in late 2017. The first tranche of Chinooks will also be handed over to the IAF in mid-2019.

After first delivery, all Apaches and Chinooks will be handed over within a period of a year, Brad Rounding, senior manager of vertical lift global sales & marketing, told Shephard

Already have an account? Log in

Want to keep reading this article?

Read this Article

Get access to this article with a Free Basic Account

  • Original curated content, daily across air, land and naval domains
  • 2 free stories per week
  • Daily news round-up email service
  • Access to all Decisive Edge email newsletters
Create account

Unlimited Access

Access to all our premium news as a Premium News 365 Member. Corporate subscriptions available.

  • Original curated content, daily across air, land and naval domains
  • 14-day free trial (cancel at any time)
  • Unlimited access to all published premium news
Start your free trial
Gordon Arthur

Author

Gordon Arthur


Gordon Arthur was the Asia Pacific editor for Shephard Media. Born in Scotland and educated …

Read full bio

Share to

Linkedin